THE DEPARTMENT of Public Works and Highways (DPWH) has proposed constructing an underground stormwater detention basin at the University of Santo Tomas to help address chronic flooding along España Boulevard.
Public Works Secretary Vince Dizon and other DPWH officials inspected the campus drainage system and met with UST administrators on Tuesday, Oct. 6, to discuss the proposal.
“Our meeting with UST went very well. We presented to them the different things we are doing, including the enlargement of the inlets,” Dizon said in a media interview.
“UST has seen the importance of what we’re doing, because, you know, España has been flooding for decades,” he added.
Dizon said the proposal was under review by the University.
He also said four drainage inlets along España Boulevard had been enlarged from 0.5 meters to 1.5 meters, with the DPWH targeting improvements to 20 more inlets in October.
The department also wants to fast-track work on 72 drainage inlets across Metro Manila.
“España is a top priority. It is one of the areas that the President [Ferdinand Marcos Jr.] personally identified to me. He said that we need to help España, especially this area around UST, because it is really prone to flooding,” Dizon said.
The Varsitarian sought comment from the UST Facilities Management Office (FMO), but it had yet to respond as of posting.
UST’s existing flood-control system
UST already operates an underground stormwater detention system designed to temporarily store rainwater and reduce flooding within the campus.
The University began upgrading its drainage system in 2018, completing the first phase in 2020 and further improvements in 2024.
The system, which covers nearly all campus roads, has a reported detention capacity of about 11,000 cubic meters.
The latest DPWH proposal follows earlier government efforts to construct a much larger underground catchment facility beneath the UST Open Field to address flooding in the surrounding area.
In 2025, the Metropolitan Manila Development Authority (MMDA) and Manila city government revived a proposal to build a 72,000-cubic-meter rainwater catchment basin beneath the Open Field.
The Open Field is among four sites within UST declared national cultural treasures, raising heritage preservation concerns over proposals involving excavation beneath the grounds.
FMO Director Fr. Dexter Austria, O.P., earlier told the Varsitarian that the University had made no commitment to the city government regarding the proposal.
“We just listened to their proposal. No commitments,” Austria said.
In August 2026, President Ferdinand Marcos Jr. identified UST as one of 30 locations being considered for underground rainwater catchment facilities as part of the government’s flood-control initiatives.
The DPWH proposal comes as the government seeks additional drainage and water detention capacity to address recurring floods along España Boulevard.